Tuesday, 11 December 2012

Piers dug..

 
View from the street.


 
View of our back yard.


From the back corner looking back to the street.
4pm seemed like forever but I picked up L and we made our way out to the block.  They dug the piers today. Seeing concrete dots all over the block helped me picture how big our house is going to be. The backyard will be the perfect size for us. Easily maintained and will be used for entertaining.

Finding it hard to concentrate

Supposed to be busy at work but my mind is elsewhere, wondering what time I can leave today to go see if anything has happened on the block...wondering if we will have the piers like our neighbour's, wondering if the neighbour's block will have more work done... They are also building with EB. Hoping the weather stays clear. Roll around 4pm!

Monday, 10 December 2012

Site scraped

J rang and said EB had rung today and advised we were in construction and gave the named of our site supervisor. We had discovered that over the weekend as our EB portal had already been updated. They indicated work should start tomorrow, but this afternoon J had another phone call from our lovely land developer to say we had our site scraped today. I can't believe how excited I was to hear a pile of dirt was dumped on our land and leveled out... Woohoo!



Wednesday, 21 November 2012

Red pegs!!

The little man and I went for a drive to our block today... And we have red pegs!! Site start appointment tomorrow, it's all very exciting!

Saturday, 10 November 2012

Love love nearmap

Can you believe nearmap updated their maps again, twice in a fortnight... I hope they do this when our build starts... Here is another photo of our estate, look more progress!

Friday, 9 November 2012

Getting closer

Eden brae sent the final Pcv today, this was as a result of the da check. We have also got a date for the site start appointment. All our documents should come next week, we are to go through these with a fine tooth comb and then we sign them. Administration will be complete!! Edging closer to something happening on our block, something other than the grass growing lol

Saturday, 3 November 2012

Mixed feelings

EB rang today and said that we are looking at mid December  before our slab will start. They can't guarantee it, but will do everything they can to get this to happen... Beginning to think I should say, the slab will be down in February.

On the other hand, nearmaps have updated their maps this week. Look at the progress in our estate!!